Quick answer: There is no single fixed timeline, but the steps are predictable. If you use a City-accepted pre-approved plan, the City of San Diego says the application will be subject to a 30-day review. For other complete ADU applications on a lot that already has a home, state law gives the City 60 days to approve or deny. Electrical service is often the longest outside step: SDG&E’s own planning estimate for new electric service to an ADU is 82–266 calendar days. In a 2021 UC Berkeley survey of California ADU owners, most reported 6 to 25 months from the start of approval to a finished ADU.
General information only – confirm current rules with the City of San Diego Development Services Department.
The ADU timeline at a glance
| Step | What happens | Official time figure |
|---|---|---|
| 1. Feasibility and design | Lot check, setbacks, size, plan drawings | No official figure – depends on your design choices |
| 2. Application and completeness check | Plans submitted to Development Services; the City checks the package is complete | Not published as a fixed time |
| 3. City plan review | Ministerial review of the ADU plans | 30 days with pre-approved plans (City) · up to 60 days for a complete application on a lot with an existing home (state law) |
| 4. Fees and permit issuance | School fees and any other fees paid; permit issued | Not published as a fixed time |
| 5. Utilities (SDG&E) | New service or panel upgrade if needed | New ADU electric service: 82–266 calendar days (planning estimate) · main panel upgrade: target average 30 business days, maximum 45 (SDG&E’s part only) |
| 6. Construction and inspections | Build, City inspections, final sign-off | No official San Diego figure |
Step 1 – Feasibility and design
Before anything is drawn, confirm the basics for your lot: detached or attached, size limit and setbacks. Our guide to detached vs attached ADUs in San Diego covers the differences, and JADU vs ADU explains the smaller junior option. This is the step you control most – and choosing between a custom design and a pre-approved plan is the biggest timing decision you make here.
Step 2 – Pre-approved plans vs a custom design
The City of San Diego accepts pre-approved ADU plans, including the County of San Diego standard plans, the City of Chula Vista standard plans and the City of Encinitas permit-ready plans. The City states that applications using pre-approved plans will be subject to a 30-day review, and that applicants must contact the ADU provider directly to find the cost to license the plan. A custom design fits your lot and taste better but goes through the standard review.
Step 3 – City review: the 30-day and 60-day rules
- Pre-approved plans: 30-day review (City of San Diego ADU page).
- Other complete applications: where the lot already has a single-family or multifamily home, the City must approve or deny a completed ADU application within 60 days (Gov. Code §66317; HCD ADU Handbook, March 2026).
- If the City does not act in time: under §66317 the application is deemed approved.
- If you ask for a delay: the 60-day period is paused (tolled) for the length of the delay.
- If the application is denied: the City must give a full set of comments listing the items that are defective or deficient, so they can be fixed and resubmitted.
The clock starts with a complete application. The City’s own timeline page notes that the actual time to process applications will vary depending on the number of applications received and the completeness of the documents submitted – so incomplete plans and correction rounds are a common reason reviews take longer than expected. See our step-by-step guide to getting an ADU permit in San Diego.
Step 4 – Fees before the permit is issued
- School fees: the City’s Information Bulletin 400 (January 2026) states that ADUs and JADUs are subject to payment of school fees. Under state guidance, school districts may levy these fees only on ADUs larger than 500 sq ft of interior living space.
- Impact fees: under state law, an ADU with 750 sq ft of interior living space or less is exempt from impact fees (HCD ADU Handbook).
For budget planning, read our ADU cost in San Diego guide.
Step 5 – Utilities: plan for SDG&E early
- New electric service for an ADU: SDG&E lists 82–266 calendar days as a planning estimate (61–274 for single-family homes).
- Main panel upgrade: SDG&E’s energization guide gives a target average of 30 business days and a maximum of 45 – for the work SDG&E is responsible for.
Because this can run longer than the City review, start the utility conversation as soon as your design shows the electrical load.
Step 6 – Construction and inspections
There is no official San Diego figure for build time alone; it depends on whether the ADU is detached or attached, a garage conversion or new construction, site work and inspections. The best broad data point is a UC Berkeley Center for Community Innovation survey (2021) of California owners whose ADUs were built in 2018–2019. Asked how many months it took from the start of approval to completion (660 answers): 1–5 months 14% · 6–10 months 28% · 11–15 months 25% · 16–20 months 14% · 21–25 months 19%. The authors note their respondents are not representative of all ADU owners, so treat these as a rough statewide picture – not a San Diego figure and not a promise. If you are building to rent, see the San Diego ADU rental rules.
What speeds an ADU up – and what slows it down
Speeds it up: a pre-approved plan; a complete, correct application the first time; an early utility check; one team handling design, permits and construction.
Slows it down: correction rounds; requesting delays (the 60-day clock pauses); a new service or panel upgrade; design changes after submission.
How NJ Design & Build helps
NJ Design & Build is a San Diego ADU builder that handles every step in-house – design, permits and construction – for detached, attached, two-story, garage-conversion and junior ADUs. We are based at 3675 Ruffin Rd, Suite 225, in Kearny Mesa and are a licensed California contractor (CA Lic. #1089207). Every project gets a written estimate after a free site visit. Talk to an ADU contractor in San Diego.
Frequently asked questions
How long does the City of San Diego take to approve an ADU?
Applications that use a City-accepted pre-approved plan are subject to a 30-day review. For other complete ADU applications on a lot that already has a single-family or multifamily home, state law gives the City 60 days to approve or deny.
What happens if the City misses the 60-day deadline?
Under California Government Code §66317, if the City has not approved or denied a completed application within 60 days, the application is deemed approved. If the applicant asks for a delay, the 60-day clock pauses for the length of that delay.
Is a pre-approved ADU plan faster?
The City reviews applications that use pre-approved plans in 30 days. You still need to contact the plan’s provider to license the plan for your own ADU.
What is usually the longest step?
It varies by project. Utility work can take a long time: SDG&E’s planning estimate for new electric service to an ADU is 82–266 calendar days.
General information only – confirm current rules with the City of San Diego Development Services Department.
Sources
- City of San Diego – Companion and Junior Units (ADU/JADU)
- City of San Diego – Information Bulletin 400 (January 2026)
- City of San Diego – Permit timelines
- California HCD – ADU Handbook (March 2026)
- California Government Code §66317
- SDG&E – SB 1210 estimated costs and timelines for new service
- SDG&E – Energization timeline guide
- UC Berkeley Center for Community Innovation – Implementing the Backyard Revolution (2021)